Safety and Protection

​The following requirements for a SSEG installation are further applicable: 

  • For all installations of any given size, a Residual Current Device Detector in line with IEC shall be installed on the circuit connecting the PV array. It shall be located between the inverter and the customer’s installation.
  • The applicant shall be responsible for ensuring that the installation complies with the Occupational Health and Safety Act (Act 85 of 1993) or relevant safety legislation. The applicant shall also forward the details of the appointee or certificate of compliance, duly completed and signed by the ECSA registered electrical engineer / technician, to eThekwini Municipality.
  • The upstream protection devices shall be coordinated with the protection installation of your installation. The details hereof shall be made available to you for co-ordination purposes. The applicant will provide overcurrent and earth fault protection that is capable of isolating the applicant’s network from eThekwini Municipality’s supply in the event of a fault on your netwo​rk.
  • All equipment from the electrical grid up to the point of metering (also referred to as point of connection) shall be provided, installed, operated and maintained by eThekwini Municipality. 
  • The applicant will, at their own expense, provide, erect, connect, operate and maintain all circuits required to connect their electrical installation to the point(s) of connection and equipment necessary for controlling such circuits. This will be undertaken to the reasonable satisfaction of eThekwini Municipality.  
  • The applicant shall be responsible for all costs including, installation, maintenance and operation of their own SSEG plant.
  • ​Prior to commissioning the plant, the engineer shall perform test(s) as per eThekwini Municipality’s commissioning report and thereafter, furnish eThekwini Municipality with the signed commissioning form indicating the results of the test(s) performed before the equipment may be permanently connected. EThekwini may request for such tests to be performed in the presence of an authorized municipal official. 

WEATHER

Cannot retrieve the URL specified in the XML Link property. For more assistance, contact your site administrator.

IMPORTANT NUMBERS
Fire Department & Metro Police:
031 361 0000
Water and Traffic Hotline:
080 131 3013
Electricity Contact Centre:
080 13 13 111
QUICK LINKS
CITY MAPS
City Maps
FOLLOW US
Find us on Facbook   YouTube   follow us on twitter  
ABOUT DURBAN   |   CITY GOVERNMENT   |   SERVICES   |   ONLINE TOOLS   |   MEDIA & PUBLICATION   |   RESOURCE CENTRE   |   PAY COUNCIL BILLS

Home | Privacy policy | Disclaimer | Sitemap | Vacancies | Contact us

© eThekwini Municipality 2011